Schifman Suggestions for SPEED Act Improvements: Focus on PIs

 

It’s not often that we get the views of former DOJ trial attorneys on permitting. Ben Schifman wrote this piece on Green Tape.

In 2021, after investing tens of millions of dollars and a decade of development, Ormat Technologies received federal approval to build the Dixie Meadows Geothermal Project: a zero-emission, baseload power project located on Bureau of Land Management (BLM) land. Two days before Ormat planned to break ground, a federal judge halted the project; it remains unfinished to this day.

The lawsuit challenging the project alleged (among other things) that the environmental review under the National Environmental Policy Act (NEPA) was not sufficient. From the bench, the Judge was unusually candid about whether he thought the Plaintiffs were likely to prevail on this claim, stating: “I really can’t say as I sit here whether there is a strong likelihood of success on the merits.” He issued a preliminary injunction — stopping the project — regardless.

The Ninth Circuit ultimately stayed the injunction, and Ormat began construction. But the “litigation doom loop” — a cycle of agency review, litigation, judicial remedy, and then more review — had begun. Following the injunction, the Plaintiffs sought an emergency endangered species listing for the Dixie Valley toad in April 2022, which created an entirely new permitting obstacle. Ormat again halted construction, and then downsized the facility to 20% of its original capacity. In 2023 BLM began a supplemental NEPA review. As of late 2025, more than four years after BLM’s original approval, and a decade after Ormat’s permit application, the project remains unbuilt. Ormat is now suing the Fish and Wildlife Service over the toad’s listing, while BLM has attempted to fast-track the project under emergency permitting procedures — which have themselves drawn threats of new litigation.

A single preliminary injunction, issued by a judge who openly doubted the plaintiffs’ ultimate likelihood of success in their lawsuit, triggered a chain of events that may have effectively killed a zero-carbon energy project bringing much needed 24-7 baseload power to the grid — all before any court determined that BLM actually violated the law.

This is an example of the litigation doom loop. And because the SPEED Act, the most significant NEPA reform effort in decades, does not address preliminary injunctions, it doesn’t fully solve it — even in NEPA cases.

****************

And here are some of his suggested solutions:

Here are some complementary reforms Congress should consider, which I describe in more detail in a longer piece.

1. Prompt filing requirement

Preliminary injunctions are especially damaging when a plaintiff waits months or years after the challenged decision is made — often after construction has begun — for the purpose of maximizing disruption or leverage.

Existing case law generally recognizes that a plaintiff’s delay in seeking emergency relief undermines a claim of irreparable harm. For instance, in Quince Orchard Valley Citizens Association v. Hodel, the Fourth Circuit held that a plaintiff’s “unexcused delay” in seeking a preliminary injunction is strong evidence that the alleged harm is not actually “irreparable.”9 The logic is intuitive: if an injury is truly imminent and irreparable, a diligent plaintiff would not sit on their rights for months.

But because “promptness” is currently just one of many discretionary factors courts weigh, it hasn’t reliably deterred strategic delay. Congress should codify a rebuttable presumption that any motion for a preliminary injunction filed more than 30 days after the challenged final agency action carries a presumption that the harm is not irreparable. Plaintiffs could rebut this presumption by showing that their delay was not strategic but rather caused by inadequate public notice or significant new information that was not reasonably discoverable within the 30-day window.

This would turn a discretionary judicial factor into a clear legal deadline, motivating opponents to bring challenges forward immediately so they can be resolved more promptly and with less disruption.

2. Multiplicative merit standard

Under current law, to obtain a preliminary injunction, a plaintiff must show a “likelihood of success on the merits.” But courts often evaluate this factor by looking at the plaintiff’s strongest single argument — even when the plaintiff must clear several independent legal hurdles to ultimately prevail.10

The Fourth Circuit identified this problem in the 2025 decision American Federation of Teachers v. Bessent.11Judge Richardson, writing for the majority, argued that when a plaintiff must prevail on several independent, dispositive issues — such as establishing standing, proving final agency action, and winning on the merits — the overall likelihood of success is not the probability of winning the strongest argument. It is the product of the probabilities of succeeding on every dispositive issue.

As the court illustrated, even if a plaintiff is a 3:1 favorite (meaning a 75% chance) on five distinct legal hurdles, the probability of running the table on all five is only about 24%. A plaintiff who is likely to win any single issue can still be a 3:1 underdog in the case overall.

Congress should codify this framework, requiring courts to determine the cumulative probability of success across all independent, dispositive issues and issue written findings specifying the estimated probability assigned to each. This ensures that preliminary injunctions — “extraordinary remedies never awarded as of right” — are reserved for cases where the plaintiff is truly likely to prevail on the merits of the case, not just on a single high-profile merits issue the court may never reach.

3. Prejudicial error standard for preliminary injunctions

Under current law, plaintiffs can obtain injunctions to halt work based on procedural errors that likely wouldn’t change the outcome. If an environmental assessment omitted discussion of an issue but the agency would have reached the same decision anyway, what purpose is served by a preliminary injunction halting the project?

Congress should require plaintiffs seeking preliminary injunctions in NEPA cases to demonstrate not just a likelihood of success in showing a NEPA violation, but a likelihood of success in showing the violation was prejudicial — meaning there’s a reasonable possibility the error affected the agency’s substantive decision.

Requiring plaintiffs to show prejudice is consistent with the Administrative Procedure Act and with recent dicta from the Supreme Court in the recent Seven County Infrastructure Coalition case that I have written about here.12 This reform would preserve preliminary relief for cases where the NEPA violation genuinely calls the agency’s decision into question.

Reforming preliminary injunctions in NEPA cases isn’t enough

The reforms proposed above would help prevent issuance of preliminary injunctions that are brought in cases where a plaintiff is unlikely to prevail or where irreparable harm is not likely. But reforming preliminary injunction standards in NEPA cases alone is not sufficient to break the “doom loop” that limits America’s ability to build infrastructure. Most major infrastructure projects that are subject to litigation are challenged under multiple statutes simultaneously: NEPA alongside the Endangered Species Act, the Clean Water Act, the National Historic Preservation Act, and others. The Dixie Meadows lawsuit — which involved numerous claims aside from those brought under NEPA — illustrates this dynamic.

NEPA-specific reforms like the SPEED Act cannot reach injunctions grounded in other federal statutes, and real-world litigation rarely presents pure NEPA claims. Still, NEPA is among the most frequently litigated permitting statutes, and it is the claim most commonly deployed for strategic delay precisely because its procedural nature makes violations easy to allege and difficult to disprove quickly. Reforming preliminary injunctive relief in NEPA cases would narrow the attack surface available to litigants pursuing delay, and provide a blueprint for similar reforms to remedies available through other laws.

While permitting reform efforts like the SPEED Act are wise to focus on final judgments, they should not be blind to preliminary remedies. Imposing reasonable limits at each stage can ensure that NEPA litigation serves its intended purpose — allowing agencies and the public to be informed about the environmental impacts of federal decisions — rather than functioning as a mechanism to delay the infrastructure our country needs to meet the challenges of the coming century.

************

Schifman also says that judicial deadlines have a history of not working.

But will courts comply with these deadlines? History suggests they likely will not.

Congress has tried mandating judicial deadlines before. The Speedy Trial Act generally requires criminal trials to begin within 70 days of indictment — yet courts routinely grant continuances.5 The Antiterrorism and Effective Death Penalty Act (AEDPA) imposed timelines for habeas corpus decisions; courts regularly exceed them.6 The Supreme Court has characterized such statutory deadlines “directives” rather than rigid jurisdictional limits.7

Federal judges have existing dockets and competing priorities — including criminal cases where there is not only a statutory but also a constitutional right to a speedy trial. Judges also have limited resources. District court filings have grown by 30% since 1990 but judgeships increased by only 4% in that time. The number of civil cases pending more than three years has risen 346% in the last 20 years.

Under these circumstances, Congressional deadlines without accompanying resources for the judiciary are unlikely to make a difference. Federal judges have lifetime tenure and Congress has never impeached a federal judge over missed deadlines (indeed, only 15 judges have ever been impeached). Ultimately, nothing in the SPEED Act guarantees courts will adhere to its deadlines. And if they don’t, a preliminary injunction granted at the start of a lawsuit could last for months — or even years

1 thought on “Schifman Suggestions for SPEED Act Improvements: Focus on PIs”

  1. Another lesson from all this is that managers should do what they can to avoid litigation. I doubt if it’s often a surprise to get sued, and many times it’s a calculated risk. (Included in the calculation is that litigation lets you blame someone else.)

    “Plaintiffs could rebut this presumption by showing that their delay was not strategic…” Is there any factual basis for a presumption that delay in filing for an injunction is usually strategic? My impression is that it has more to do with attorney workload and availability and the fact that implementation doesn’t necessarily follow immediately upon a decision (and sometimes gets scuttled entirely). These recommendations might encourage suing when it’s not really necessary. Am I wrong?

    Reply

Leave a Comment

Discover more from The Smokey Wire : National Forest News and Views

Subscribe now to keep reading and get access to the full archive.

Continue reading